University Ave. Crosswalk Improvements
Project ID:
TS-01035
Project Category:
Pedestrian and Bicycle Safety
Project Status:
Completed
Project Priority:
Asset Preservation
Project Lead:
D. Varela
2016
September 2017
See map: Google Maps
This project will make improvements to two consecutive interchanges located on University Avenue at Lincoln Avenue and Burke Road. The intersections are to be improved to provide better pedestrian access to nearby schools, downtown Los Altos, Lincoln Park and nearby churches. The improvements include replacement or installation of curb ramps, a raised crosswalk, flashing beacon system, new crosswalks and removal of ADA barriers. The improvements will enhance pedestrian safety and overall pedestrian access by improving visibility and connectivity.
Project Estimates | Prior Appropriations |
2017/18 Budget | 2018/19 Planned | 2019/20 Planned | 2020/21 Planned | 2021/22 Planned | Total |
University Ave. & Lincoln Ave. Crosswalk Improvements | $324,000 | - 0 - | - 0 - | - 0 - | - 0 - | - 0 - | $324,000 |
Funding Sources | |||||||
CIP | $154,000 | - 0 - | - 0 - | - 0 - | - 0 - | - 0 - | $154,000 |
CDBG | $170,000 | - 0 - | - 0 - | - 0 - | - 0 - | - 0 - | $170,000 |
Status Updates
Monday, July 17, 2017: Please see below for the latest project schedule:
Dates | Work |
---|---|
7/12 (Wed) - 7/17 (Mon) | Demolition |
7/17 (Mon) - 7/28 (Fri) | Grading / Utility Work |
7/28 (Fri) - 8/2 (Wed) | Install Curb & Gutter |
8/2 (Wed) - 8/24 (Thur) | Install Ramps |
8/9 (Wed) - 8/25 (Fri) | Asphalt Work |
8/25 (Fri) - 9/1 (Fri) | Install Poles, Signs, Striping |
9/1 (Fri) - 9/7 (Thur) | Wrap-Up |