This project will make improvements to two consecutive interchanges located on University Avenue at Lincoln Avenue and Burke Road. The intersections are to be improved to provide better pedestrian access to nearby schools, downtown Los Altos, Lincoln Park and nearby churches. The improvements include replacement or installation of curb ramps, a raised crosswalk, flashing beacon system, new crosswalks and removal of ADA barriers. The improvements will enhance pedestrian safety and overall pedestrian access by improving visibility and connectivity.

Project Estimates Prior
Appropriations
2017/18 Budget 2018/19 Planned 2019/20 Planned 2020/21 Planned 2021/22 Planned Total
University Ave. & Lincoln Ave. Crosswalk Improvements $324,000 - 0 - - 0 - - 0 - - 0 - - 0 - $324,000
Funding Sources
CIP $154,000 - 0 - - 0 - - 0 - - 0 - - 0 - $154,000
CDBG $170,000 - 0 - - 0 - - 0 - - 0 - - 0 - $170,000

 

 

 

 

 

 

Status Updates

Monday, July 17, 2017: Please see below for the latest project schedule:

Dates Work
7/12 (Wed) - 7/17 (Mon) Demolition
7/17 (Mon) - 7/28 (Fri) Grading / Utility Work
7/28 (Fri) - 8/2 (Wed) Install Curb & Gutter
8/2 (Wed) - 8/24 (Thur) Install Ramps
8/9 (Wed) - 8/25 (Fri) Asphalt Work
8/25 (Fri) - 9/1 (Fri)  Install Poles, Signs, Striping
9/1 (Fri) - 9/7 (Thur) Wrap-Up