Sewer System Repair Program

Project ID: 
WW-01001
Project Category: 
Sewer
Project Status: 
Ongoing
Project Priority: 
Asset Preservation
Project Lead: 
T. Nguyen
Year Adopted:
Annual Project
Target Completion Date:
Annual Project
Los Altos, CA 94022

The 2013 Sanitary Sewer Master Plan Update recommended replacement of segments of pipes located at various locations throughout the City that are included in the 30-day focused cleaning schedule that have severe sags. Such sags can cause accumulation of debris and grease which necessitates frequent cleaning.

Project Estimates Prior
Appropriations
  2020/21 Budget 2021/22 Planned 2022/23 Planned 2023/24 Planned Total
Sewer System Repair Program $0   $620,000 $630,000 $640,000 $650,000 $2,540,000
Funding Sources
Sewer Fund $0   $620,000 $630,000 $640,000 $650,000 $2,540,000