This project will continue efforts to improve ADA accessibility at public facilities throughout the City. This would include ramps at various intersections throughout the City, correct existing sidewalks that have inadequate access for wheelchair facilities, ADA-compliant pedestrian push buttons at City street intersections and also improve accessibility by replacing pedestrian paths of travel that are uplifted, cracked, too narrow, or otherwise out of compliance with current ADA requirements.

Work will be based on a prioritization list developed by the City’s Bicycle/Pedestrian Advisory Commission. Efforts will be directed towards improving accessibility at locations needed by disabled individuals, with an emphasis on improving pedestrian and bicycle safety.

ADA compliance is a federal requirement and the City is refreshing and updating its compliance standards in this year.

Project Estimates Prior
Balance
2013/14 2014/15 2015/16 2016/17 2017/18 Total
ADA Accessibility $384,261 $60,000 $60,000 $60,000 $60,000 $60,000 $684,261
Funding Sources
Community Development Block Grant $384,261 $60,000 $60,000 $60,000 $60,000 $60,000 $684,261

 

 

 

 

 

 

ADA Accessibility (Project TS-01008)
ADA Accessibility Project Map
Status Updates
Wednesday, October 8, 2014:

Beginning Wednesday, October 8 through Friday, October 31, the southbound lane of San Antonio Road between Whitney Street and Parking Plaza South (in front of the Los Altos Grill) will be closed between the hours of 9:00 a.m. and 3:00 p.m. The lane closure is necessary to allow for the removal and replacement of curb, gutter, sidewalk and ramps per ADA compliant standards. Traffic control measures will be in place.