Waterline Backflow Preventers

Project ID: 
CF-01016
Project Category: 
Building
Project Status: 
Not Started
Project Priority: 
Asset Preservation
Expended to Date: 
$46,279
Project Lead: 
M. Hernandez
Year Adopted:
2016
Target Completion Date:
December 2017

The project will install backflow preventers for all City-metered water connections. The Cross Connection Control Program is designed to meet the requirements of the California Code of Regulations, Title 17, Public Health Sections 7583 through 7605. Failure to install and maintain such devices may lead to a water service interruption and possible loss of water services.

Project Estimates Prior
Appropriations
2017/18 Budget 2018/19 Planned 2019/20 Planned 2020/21 Planned 2021/22 Planned Total
Waterline Backflow Preventers $220,000 - 0 - - 0 - - 0 - - 0 - - 0 - $220,000
Funding Sources
CIP $220,000 - 0 - - 0 - - 0 - - 0 - - 0 - $220,000