Structural Reach Replacement, PCR (a)

Project ID: 
WW-01002
Project Category:
Project Status: 
In Construction
Project Priority: 
Health & Safety
Expended to Date: 
$58,730
Project Lead: 
A. Fairman
Year Adopted:
2013
Target Completion Date:
Ongoing
Citywide
Los Altos, CA 94022/94024

The 2013 Sanitary Sewer Master Plan Update recommended replacement of segments of pipes at various locations throughout the City that typically have multiple moderate-to-severe  structural defects (Pipe Condition Rating A). Costs are based on the open-trench method of repair because defects include sags which are difficult to correct using trenchless repair methods. The areas selected for replacement were identified in closed circuit video inspections accomplished from 2007 through 2010.  This project has five phases beginning in FY 2013/14 to repair these segments.

Project Estimates Prior
Appropriation
2016/17 Budget 2017/18 Planned 2018/19 Planned 2019/20 Planned 2020/21 Planned Total
Structural Reach Replacement, PCR (a) $1,747,704 $700,000 $800,000 $800,000 $800,000 $800,000 $4,874,704
Funding Sources
Sewer Fund $1,747,704 $700,000 $800,000 $800,000 $800,000 $800,000 $4,874,704

 

 

 

 

 

 

Structural Reach Replacement, PCR (a)
Structural Reach Replacement, PCR (a)

Status Updates

Friday, July 29, 2016: The Structural Reach Replacement Project will begin the week of August 2, 2016 and is the second of two sewer projects that will be under construction this summer. This project replaces segments of pipes throughout the City which have been identified to have moderate to severe structural defects. Next week, the City will pilot a new replacement method called “Pipe Reaming” on the first segment of the project on Austin Avenue. Pipe reaming is a trenchless pipe replacement process that has been successful in neighboring agencies and if successful here would provide the City with another valuable option to perform this type of work.

Friday, December 2, 2016: This week, the City’s contractor, EPS Inc. dba Express Plumbing performed work on the replacement of the sewer main on Dracena Lane using the pipe reaming method. Next week, the contractor will change locations and begin work on St. Charles Court.

Friday, December 9, 2016: This week, the City’s contractor, EPS, Inc. dba Express Plumbing began work on the replacement of the sewer main on St. Charles Court using the pipe reaming method. Work will continue into next week in this area. This capital improvement project replaces segments of pipes throughout the City which have been identified as having moderate to severe structural defects.  

Friday, December 23, 2016: This week, the City’s contractor, EPS, Inc. dba Express Plumbing completed work on the replacement of the sewer main on Granger Avenue and following the holiday break will begin work on Stonehaven Drive.