First Street Resurfacing

Project ID: 
Project Category:
Project Status: 
Not Started
Project Priority: 
Asset Preservation
Expended to Date: 
- 0 -
Project Lead: 
V. Chen
Year Adopted:
Target Completion Date:
First Street
Between State Street & Edith Avenue
Los Altos, CA 94022

This project dedicates annual street resurfacing dollars to the tail end of Phase II First street improvements.

It places an overlay of asphalt concrete (AC) on existing street surfaces from State Street to Edith Avenue after all sidewalk and other street adornments are completed both by the City and private developers (Safeway and Lennar Homes). The project naturally completes the phase I process that included the resurfacing from Main to State Street. Cutouts and repairs of pavement failures, grinding down pavement at outer edges and/or curbs may be included.  Activities may also include the installation of pavement fabric in addition to pavement striping and stenciling after the resurfacing.  Damaged curb, gutter and/or minor drainage improvements can also be included in this project.
This street improvement will assist in the City-wide effort to maintain a superior ranking of the condition of all the streets in the City.

Project Estimates Prior
2013/14 2014/15 2015/16 2016/17 2017/18 Total
First Street Resurfacing - 0 - $300,000 - 0 - - 0 - - 0 - - 0 - $300,000
Funding Sources
CIP - 0 - $300,000 - 0 - - 0 - - 0 - - 0 - $300,000


First Street Resurfacing Map
First Street Resurfacing Map