Fallen Leaf Lane Sewer Main Replacement
Project ID:
1115
Project Category:
Sewer
Project Status:
Completed
Expended to Date:
$2,056,910
Project Lead:
A. Fairman
2011
Spring 2014
Completion Date:
April 2013
Fallen Leaf Lane at Fremont Avenue
Los Altos,
CA
94024
See map: Google Maps
The City of Los Altos completed three sewer main repair and replacement projects in order to ensure the ongoing efficiency of the City’s sewer needs. The scope of work to be completed included the following:
|
|
Project Estimates | Prior Balance |
2013/14 | 2014/15 | 2015/16 | 2016/17 | 2017/18 | Total |
Fallen Leaf Lane | $574,248 | - 0 - | - 0 - | - 0 - | - 0 - | - 0 - | $574,248 |
Funding Sources | |||||||
Sewer Fund | $574,248 | - 0 - | - 0 - | - 0 - | - 0 - | - 0 - | $574,248 |