Annual Sewer Repair

Project ID: 
1304
Project Category: 
Sewer
Project Status: 
Completed
Project Lead: 
A. Fairman
Year Adopted:
2013
Target Completion Date:
Summer 2014
San Antonio Frontage Road and El Monte Avenue
Los Altos, CA 94022

The City of Los Altos sewer main repairs consist of lining the underground sanitary sewer pipes at locations noted below to mitigate corrosion. The project will also include sewer manhole rehabilitation at a couple of locations in the street on Bayshore Parkway.  The City of Los Altos awarded the construction contract to Insituform Technologies, LLC for this work.

The contractor will install “no parking” barricades as necessary in the area and will provide notices to the residents and/or businesses when work commences. This pipeline work and the manhole rehabilitation will not require digging.   All work will take place within the public right-of-way and no access to private property will be necessary.

The pipeline work cannot be accomplished when there is wastewater flowing in the pipe. Therefore, there will be an aboveground bypass piping system installed in the street or in the street shoulder area between each of the pipeline segments that will be lined.

The sanitary sewer pipes at the following locations will be repaired:

  1. San Antonio Frontage Road - 996 San Antonio Road to 998 San Antonio Road
  2. San Antonio Frontage Road/Easement - 998 San Antonio Road to 4007 Transport Street
  3. Easement at 4007 Transport Street/under State Highway 101 - 4007 Transport Street, under State Highway 101, to 2634 Bayshore Parkway
    The bypass piping for the sewer segments 1 through 3 (listed above) will be installed between the manhole on northbound San Antonio Road, located across from 870 San Antonio Road, north of E. Charleston Road, to the manhole at 1120 San Antonio Road, across from 1157 San Antonio Road and north of Bayshore Driveway.  The bypass piping will need to be in place until all three sewer segments have been lined and until the two manholes on Bayshore Parkway have been rehabilitated.
  4. El Monte Avenue – Intersection of El Monte Avenue and Hollingsworth Drive to the intersection of El Monte Avenue and Pilgrim Avenue
  5. El Monte Avenue - Intersection of El Monte Avenue and Pilgrim Avenue to intersection of El Monte Avenue and Marich Way
Project Estimates Prior Balance 2013/14 2014/15 2015/16 2016/17 2017/18 Total
Annual Sewer Repair $369,000 - 0 - - 0 - - 0 - - 0 - - 0 - $369,000
Funding Sources
Sewer Fund $369,000 - 0 - - 0 - - 0 - - 0 - - 0 - $369,000

 

Project Community Impact
The construction of these projects is estimated to start and end in the spring of 2014.  The contractor will provide traffic control devices during construction, including detour signs as necessary.

For questions about this project, please contact the Engineering Division at (650) 947-2780.

Files: