FALLEN LEAF LANE SEWER MAIN REPLACEMENT

DESCRIPTION:

This project provides for the replacement of 2,250 feet of existing 6-inch sewer pipe with new 8-inch sewer pipe. The project is identified as Project H2 and scheduled for FY 2010/2011 in the Sewer Master Plan. The replacement will most likely be done using open trench methods.


COST SUMMARY:
Design and Construction $ 430,000

POTENTIAL FUNDING SOURCES:
Sewer Enterprise Fund $ 430,000

IMPACT ON ANNUAL MAINTENANCE AND OPERATION COSTS:
Maintenance costs should be reduced once the new mains are in place.

ALTERNATIVES:
None