DESCRIPTION:
This project provides for the replacement of 2,250 feet of existing 6-inch sewer pipe with
new 8-inch sewer pipe. The project is identified as Project H2 and scheduled for FY
2010/2011 in the Sewer Master Plan. The replacement will most likely be done using
open trench methods.
COST SUMMARY:
| Design and Construction |
$ |
430,000 |
POTENTIAL FUNDING SOURCES:
| Sewer Enterprise Fund |
$ |
430,000 |
IMPACT ON ANNUAL MAINTENANCE AND OPERATION COSTS:
Maintenance costs should be reduced once the new mains are in place.
ALTERNATIVES:
None
|
|
|
| |